Wynn Resorts Logistics Warehouses

Wynn Resorts Logistics Warehouses

Location

RAS AL KHAIMAH, UAE

Year

2026

Area

36,000 m²

Type

New build

The brief

Two Grade A logistics warehouses for Wynn Resorts in Ras Al Khaimah, with Phase 1 taken from staking out the plot to completion in 153 days.

Client

Wynn Resorts

Warehouse 1

19,000 m²

Warehouse 2

17,000 m²

Total area

36,000 m²

Phase 1 programme

153 days

Delivery

Design & build

Challenges

Wynn Resorts needed Grade A logistics space in place quickly to support its development in Ras Al Khaimah. Two warehouses totalling 36,000 m² had to go from staking out the plot to completion of Phase 1 in 153 days, with design, approvals and construction running in tight sequence.

What we did

We delivered the facility design and build with a trusted contractor partner, sequencing design, approvals and construction tightly to protect the programme.

The result

Phase 1 was completed 153 days after the plot was staked out, and Wynn Design & Development has provided a written reference for Waterville.

The facility

Two Grade A logistics warehouses of 19,000 m² and 17,000 m², serving Wynn Resorts in Ras Al Khaimah.

Pace

Phase 1 went from staking out the plot to completion in 153 days, delivered design and build with our contractor partner.

  • 2 warehouses, 36,000 m² in total

  • Phase 1 in 153 days

  • Written reference from Wynn Design & Development

WATERVILLE

& Co.

Contact

jonathan@watervilleandco.com

+971 50 469 1980

+44 7770 990000 - WhatsApp

Waterville Consultancy L.L.C · Dubai, UAE · Trade Licence 1227231 · © 2026

WATERVILLE

& Co.

Contact

jonathan@watervilleandco.com

+971 50 469 1980

+44 7770 990000 - WhatsApp

Waterville Consultancy L.L.C · Dubai, UAE · Trade Licence 1227231 · © 2026

/

/

Wynn Resorts Logistics Warehouses

Wynn Resorts Logistics Warehouses

Location

RAS AL KHAIMAH, UAE

Year

2026

Area

36,000 m²

Type

New build

The brief

Two Grade A logistics warehouses for Wynn Resorts in Ras Al Khaimah, with Phase 1 taken from staking out the plot to completion in 153 days.

Client

Wynn Resorts

Warehouse 1

19,000 m²

Warehouse 2

17,000 m²

Total area

36,000 m²

Phase 1 programme

153 days

Delivery

Design & build

Challenges

Wynn Resorts needed Grade A logistics space in place quickly to support its development in Ras Al Khaimah. Two warehouses totalling 36,000 m² had to go from staking out the plot to completion of Phase 1 in 153 days, with design, approvals and construction running in tight sequence.

What we did

We delivered the facility design and build with a trusted contractor partner, sequencing design, approvals and construction tightly to protect the programme.

The result

Phase 1 was completed 153 days after the plot was staked out, and Wynn Design & Development has provided a written reference for Waterville.

The facility

Two Grade A logistics warehouses of 19,000 m² and 17,000 m², serving Wynn Resorts in Ras Al Khaimah.

Pace

Phase 1 went from staking out the plot to completion in 153 days, delivered design and build with our contractor partner.

  • 2 warehouses, 36,000 m² in total

  • Phase 1 in 153 days

  • Written reference from Wynn Design & Development

WATERVILLE

& Co.

Contact

jonathan@watervilleandco.com

+971 50 469 1980

+44 7770 990000 - WhatsApp

Waterville Consultancy L.L.C · Dubai, UAE · Trade Licence 1227231 · © 2026